Thwaites Ltd – Over-Roof and New Build

Project Overview

Thwaites Ltd, a leading manufacturer of site dumpers, undertook a significant redevelopment at their Cubbington facility to improve supply chain operations and support their production line expansion. Delivered over two distinct phases by 1 Eighty Roofing Solutions, the project involved a combination of over-roofing and new-build cladding works spanning over 12,000m2 across multiple structures.
● Phase 1: 5,000 m2 over-roof to existing Building B3
● Phase 2: 4,200 m2 new-build roof – Tata Platinum Plus specification
1,800 m2 new-build walls – Tata Platinum Plus

Timeline
● Phase 1: 2 April – 14 June 2024 (42 days)
● Phase 2: 18 November 2024 – 14 March 2025 (75 days)
Both phases were delivered on time and defect free, despite demanding site conditions and seasonal challenges.

LWD 3654-7
Challenges

Phase 1: Installation over a live production facility required careful sequencing, coordination, and speed to minimise disruption.
Tight Programmes: Both phases had limited durations, with zero margin for delay.
Phase 2 Winter Conditions: Cold weather and shorter daylight hours added logistical pressure.

DJI_0433
DJI_0282
DJI_0820
DJI_0819

Fixing Point’s Involvement

Fixing Point supplied a full envelope of Tata-approved components, ensuring seamless specification compliance and build quality:
● Gridtite Spacer System for speed and alignment
● Moulded Head FP+ Stainless Fixings for durability and warranty assurance
● FP+ Sealants and EPDM Fillers for weatherproofing and detail closure

LWD 3654-18
LWD 3654-3
LWD 3654-7
LWD 3654-8

Collaboration and Delivery

This project marked the fifth successful partnership between Interclass Plc and 1Eighty in two years. Fixing Point worked in close coordination with the Interclass team to ensure efficient supply and ongoing support throughout the programme.


Outcome

The project was completed on schedule, fully meeting the client’s brief to support production growth while maintaining operational continuity. Fixing Point’s dependable supply, technical advice, and Tata-compliant systems ensured smooth delivery across both phases.

“The project went very well. Dealing with Fixing Point was a smooth process— the team gave me all the information I needed, and the support throughout the project was fantastic.”

Project Coordinator

Want to Know More?